Where: U.S. Route 54 over Little Dry Wood Creek west of Nevada
When: Beginning Week of Monday, May 13
Details: Project was originally scheduled to begin back in March 2024, but construction delays postponed the project
Traffic impacts:
Beginning the week of May 13, contractor crews will build temporary crossover lanes in the median, taking 3-4 weeks to complete
Once the crossover lanes are completed, contractor crews will CLOSE the westbound bridge and shift traffic head-to-head on the eastbound lanes until early August
When contractor completes work on westbound bridge, the eastbound bridge will CLOSE and traffic shifted head-to-head on the westbound lanes for duration of the project
Drivers should expect traffic delays
Watch for equipment and crews entering and exiting the work zone
Signs and message boards will alert drivers approaching the work zone
Drivers should consider alternate routes during the project
Check MoDOT’s Traveler Information Map for road closings/traffic impacts
Weather and/or construction delays could alter the work schedule.
Project information:
Prime contractor – Capital Paving and Construction LLC, Columbia
Total project cost: $2.3 million
Contract completion date: Nov. 1, 2024